Weekly Progress

Back to main page

 

FALL TERM

Week # 1

    -Wrote Project Proposal with budget and timeline

    - Continued with Literature search

    - Organized and reread the literature acquired during the summer

Week # 2

    - Created Preliminary concepts in Solid Works

    - Continued Literature search

Week # 3

    - Created concept selection criteria

    - Researched Specific Engine information (Ford Zetec engine)

    - Ordered Haynes Workshop Manual

Week # 4

    - Selected appropriate material for transparent cylinder namely UV transmitting Vycor 7913 from Corning INC.

    - Defined the necessary boundary conditions to conduct a thermal stress study

Week # 5

    - Conducted a transient thermal stress analysis on the transparent cylinder using the given material properties

    - Analyzed the obtained results

Week # 6

    - Wrote IEF proposal

    - Analyzed COSMOS results which showed inconsistencies and were deemed to be unsatisfactory

    - Refined and finalized the necessary boundary conditions to conduct a transient thermal stress analysis in GeoStar

Week # 7

    - Started working with Prof. Bucinell to conduct transient thermal stress analysis on GeoStar

    - Analyzed the cylinder head removal procedure in order to get a better understanding and also to list the necessary tools needed to

    accomplish this task

Week # 8

    - Designed and fabricated some of the tools needed to lift engine's head up

    - Worked and prepared power point presentation for oral report

    - Ordered cylinder head gasket

Week # 9

    - Designed detailed preliminary base mount (studied several alternatives for sealing O-rings)

    - Fabricated another tool for engine lifting procedure

Week # 10

    - Worked on final MER 197 paper

    - Made a list of metric bolts to be acquired in Ecuador

 

WINTER TERM

Week # 1

    - Conducted engine's head lifting procedure in order to access hole pattern of the engine's block and head

Week # 2

    - Obtained detailed bolt and hole pattern measurements from engine block

    - Ordered new head gasket

Week # 3

    - Worked at machine shop to manufacture an aluminum plate that will allow us to confirm the bolt pattern measurements

Week # 4

    - The aluminum plate showed that the measurements were slightly off and thus needed to be corrected.

    - I decided to get the measurements from the engine head instead of the engine block. Moved the head to the machine shop.

    - Researched methods to accurately obtain bolt and hole patterns

Week # 5

    - Obtained new bolt pattern measurements

    - Manufactured a second checking plate

    - Confirmed that new hole pattern was accurate

Week # 6

    - Started working on the base mount detailed design

    - Worked with professor Bucinell to finalize the GeoStar model of the transparent cylinder and hence start conducting different studies

    - Placed the boundary conditions on the transparent cylinder (GeoStar) and started conducting the required studies

Week # 7

    - Performed numerous transient thermal stress analysis using GeoStar.

           - Sample stress results for running time of 45 seconds

    - Results started to show that UV glass would fail under the applied boundary conditions

Week # 8

    - Continued to conduct different studies trying to determine the maximum transient stress

    - Changed glass cylinder's thickness (GeoStar) from 2cm to 1.5cm and conducted new studies

    - Results showed a slight improvement (smaller stress) but UV glass still fails at very short times

Week # 9

    - Started to work on thesis

    - Talked to Jim and Roland about design ideas (sample configuration)

    - Started to look into different material for transparent cylinder in order to prevent failure

Week # 10

    - Continued to conduct studies on transparent cylinder using GeoStar

    - Run studies on sapphire cylinder which proved to be very auspicious since sapphire cylinder did not fail

    - Worked on thesis

 

Completed Thesis